June 08 2020

First stage of work to begin

June 2020

Raymer Road at Bellevue Creek to Hubbard Road: mid June to late July

Mid June to late July

July 2020

DeHart Road to Hubbard Road: early July to late August

Early July to late August

August 2020

Raymer Road to Coronado Crescent at Hubbard Road: early August to early October

Early August to early October

June 2020

Hubbard pressure reducing station: mid June to late September

Mid June to late September

July 2020

Raymer pressure reducing station: late July to early October

Late July to early October